(HDD) Complete construction of pipeline crossing under Hanoi Highway by Horizontal Directional Drilling technology (HDD), Dictrict 9, Ho Chi Minh City
25/08/2015

On 15-August-2015, Infrastructure Works Construction Enterprise, directly under UDC, completed construction of HDPE pipeline under project "Relocation of D500 water supply pipeline for area of Suoi Cai Bridge and Hanoi Highway" in application of Horizontal Directional Drilling technology. The water supply pipeline is ᴓ500 in diameter, 92m long, 7m deep under the ground, which crosses under Hanoi highway, District 9, Ho Chi Minh City.


92m HDPE D500 pipeline crossing under Hanoi Highway was installed by HDD technology, High Tech Zone, District 9, Ho Chi Minh City.

Source: Public Relation Division

 